CPR Capacity Expansion – British Columbia

PNR RailWorks constructed track at five strategic locations to add capacity on CPR's line in British Columbia.
  • Constructed 75,000 feet of new mainline and passing track
  • Installed 47 turnouts
  • Performed 1,000+ thermite welds

5 strategic locations on CPR’s mainline in British Columbia

Customer
Canadian Pacific Railway

RailWorks Business Unit
PNR RailWorks

Description
PNR RailWorks constructed new sidings, backtracks and turnouts to add capacity at five strategic CPR mainline locations in British Columbia.

Scope
PNR RailWorks constructed 75,000 feet of new mainline and passing track with concrete ties, installed 47 turnouts, including #20 crossover switches, and performed 1,000+ thermite welds. The crews mobilized to complete the new construction capacity expansion projects at Swansea, Savona, Golden, Salmon Arm and Chase along CPR’s mainline in British Columbia.

Unique features
All work was successfully completed under “rule 42” alongside active mainline track. PNR RailWorks crews worked in short, six and eight-hour work blocks to install turnouts and complete the mainline connections.